2026 Paving Maintenance Project

Current Schedule

Updated October 7, 2026. Please note this schedule is subject to change and weather dependent. Please check back often for the most current information.

The work shown below includes activities to prepare roadways prior to slurry seal, which is anticipated to take place in late September to early October. Residents will be informed 72 hours prior to slurry on their roadway.

Week of Oct 5 - Utility/Manhole Adjustments

Week of Oct 12 - Street Striping

Week of Oct 19 - Close Out

2026 Paving Maintenance Project
On Tuesday August 4, 2026, the Pismo Beach City Council awarded a contract to Pavement Coatings, Co. for $978,790.20, to perform roadway maintenance and improvements at various locations throughout the City. 


The project will address roadway repairs and pavement improvements at locations identified through a recent citywide pavement condition study. Work may include:

  • Removing and replacing damaged asphalt pavement
  • Saw-cutting, excavation, and preparation of roadway surfaces
  • Grinding or milling existing asphalt
  • Installing new hot mix asphalt (HMA) pavement
  • Applying slurry seal and other pavement treatments
  • Repairing or replacing concrete curbs, gutters, and other concrete improvements
  • Adjusting utility covers and other utility infrastructure as needed
  • Replacing roadway striping, pavement markings, and traffic signs
  • Coordinating with utility providers
  • Cleaning and restoring work areas upon completion

Project Updates

This webpage will be updated regularly throughout the project with the latest construction information. Updates will include upcoming work areas, street closures, parking restrictions, and the contractor's three-week look-ahead schedule. 

Residents in neighborhoods where construction is scheduled will also receive door hangers several day in advance of work. Please check back regularly for the latest project updates and information about upcoming construction activities.